Critical Path Method [CPM]

Venkataramiah S Annapragada
24/12/2018 0 0

 This method involves the following steps :

  • Calculate the Duration for all activities on the Task Network Diagram.
  • Calculate the early start [ES], early finish [EF], late start [LS] and Late Finish [LF] for all activities by using Forward pass and Backward pass techniques.
  • Identify the number of paths on the Network Diagram.
  • Calculate the total duration of each path.
  • Identify the path with the longest duration. This path is called Critical Path.
  • The Critical Path Duration will be the MINIMUM Project Duration.
  • Calculate Total Float for all activities with the formula [LS-ES] or [LF-EF].
  • Total Float is the amount of time an activity can be delayed without delaying the project finish date. The float is also called as Slack.
  • Identify Activities on Critical Path. These will have zero float which means they HAVE to start and finish on time.
0 Dislike
Follow 2

Please Enter a comment

Submit

Other Lessons for You

PMP(Project Management Professional)
PMP is the hottest career options for professionals in project management field. It provides project managers with certification that is helpful in their career. PMP is the most reputed certification...
S

Sprintzeal

0 0
0

Primavera P6: Changing negative symbol for currency
Project user may want to display currency in different format according to personal choice. Primavera provides one option to change it. This video explains how to change the currency display format.

What is Baseline and what is the use of baseline in MSP (Microsoft Project)
What is baseline - The baseline in MSP (Microsoft project) management refers to the first version of the schduled project (after approval on draft version) timelines (duration), cost, resource and scope....

Points to be remembered while creating Project schedule in MS Project
Rule 1 : First task should not have predecessors, Last task should not have successors. Rule 2 : Except first and last tasks, every task must have both predecessors and successors. Rule 3 : Project Summary...

Managing Successful Programs : An Overview.
Quick rundown on what are key skills & expertise that helps to manage the programs successfully. First and the most important aspect is how well we connect with our customer and how soon we speak the...
X

Looking for PMP Training Classes?

The best tutors for PMP Training Classes are on UrbanPro

  • Select the best Tutor
  • Book & Attend a Free Demo
  • Pay and start Learning

Learn PMP Training with the Best Tutors

The best Tutors for PMP Training Classes are on UrbanPro

This website uses cookies

We use cookies to improve user experience. Choose what cookies you allow us to use. You can read more about our Cookie Policy in our Privacy Policy

Accept All
Decline All

UrbanPro.com is India's largest network of most trusted tutors and institutes. Over 55 lakh students rely on UrbanPro.com, to fulfill their learning requirements across 1,000+ categories. Using UrbanPro.com, parents, and students can compare multiple Tutors and Institutes and choose the one that best suits their requirements. More than 7.5 lakh verified Tutors and Institutes are helping millions of students every day and growing their tutoring business on UrbanPro.com. Whether you are looking for a tutor to learn mathematics, a German language trainer to brush up your German language skills or an institute to upgrade your IT skills, we have got the best selection of Tutors and Training Institutes for you. Read more